The number depends on steel, cavity count and geometry – so here is the structure of the cost, not a fake single price.
IN SHORT
What actually drives the price of an injection mold, what a published budget range looks like, and how to read a quotation so you can compare two of them fairly.
| A 2-cavity ABS tool | Indicative industry range and lead time |
|---|---|
| Prototype tool (aluminium or soft steel) | About $1,500 – $5,000 · 1-3 weeks · for fit checks and 100-500 parts |
| Single-cavity production tool | About $5,000 – $15,000 · 3-6 weeks · for 1,000-50,000 parts |
| Multi-cavity tool (2-8 cavities) | About $15,000 – $50,000 · 4-8 weeks · for 50,000+ parts |
| High-cavity or complex tool | About $50,000 – $150,000 and up · 8-12 weeks · for 500,000+ parts |
| Per-part cost (material) | About $0.10 – $5.00 per part, depending on resin and part weight |
| Per-part cost (processing + inspection) | About $0.05 – $2.00 per part, mostly machine time and cycle |
| Hidden costs to watch | Design changes after steel is cut, secondary operations, mold maintenance, freight |
A total project cost is the tool, the parts and the things nobody quotes at the start: a design change after the steel is cut, painting or assembly, mold maintenance once the cavity wears, and freight. A quote that shows only the mold is not a cheap quote – it is an incomplete one.
Part size, geometry complexity (every slide, lifter and insert is money), cavity count, steel, and surface finish. A textured or mirror-polished cavity costs more than a standard one for the same geometry.
More cavities cost more to build and less per part. A 4-cavity tool can cost three times a single-cavity tool and break even at a few thousand parts. We will run the amortisation for your actual volume, because the right answer is different for 5,000 parts and 500,000.
Design for manufacture. Thinner uniform walls, no unnecessary undercuts, and a geometry that does not need slides, usually removes 20-30% of the cost before the first block of steel is bought. That is why we offer the DFM review before quoting – it is not a freebie, it is the cheapest part of the project.
COMMON QUESTIONS